PRINCETON/ONR
High Reynolds number Test Facility HRTF
CONSTRUCTION TIMELINE

1998

ONR-DURIP grant (N00014-98-I-0325) awarded to construct HRTF using concept proven in Superpipe.

April

Main electrical wiring connected

September

Arrival of motor

October 

Arrival of pump and shaft seal

Arrival of heat exchanger section

Bids for tunnel construction received

November

Crane installation complete

Motor power hook-up

Arrival and hook-up of heat exchanger section

February 1999

Order for tunnel placed

June

Heat exchanger section hook-up

July

Tunnel segments arrive from Struthers Industries

Completion of cooling water system

August

Tunnel segments bolted up

October

Venting system complete

November

APS conference New Orleans - Progress Report presented

February 2000

First run! Work on pump etc completed

Flow quality experiments begin

 

 

March

Screens arrive

Flat plate assembly completed

April

Pitot surveys of flat plate turbulent boundary layer begin

 